Mathematics Question For Railway Group D,RPF, Rajasthan SI 29-09-2018
Daily quiz, Math Short Tricks 0 CommentsRailway Group D, RPF, Recruitment 2018 will be held to recruit candidates to the post in Level 1 of 7 CPC Pay Matrix.
mathematics Related Most Question With Answer Set 230 Current Affairs, Aptitude And Join the best Online Test Series & get all India Rank, Logical Match. Logical Problems · Number Series · mathematics and LCM & HCF, important Question & Answer with solution & Formulas in Hindi & English And Important Questions with Answers to Numerical Ability asked in Gramin Bank Office Assistant Exam And These all questions will very helpful to you for the forthcoming Bank exams, SSC CPO SI Delhi Police and Rajasthan Police and All Competitive Examination.
Click: mathematics -Most Question & Answer with
Question(1) A man and a boy worked together for 5 days and he got a total of 800 rupees wages. Trivial work is more skilled than a male boy. What is daily wages of boys?
एक पुरूष और एक लड़के ने मिलकर 5 दिन काम किया और उन्हें कुल मिलाकर 800 रूपये मजदुरी प्राप्त हुई | पुरूष लड़के की अपेक्षा तिगुना कार्य कुशल है | लडके की दैनिक मजदूरी कितनी है ?
(A)44
(B)65
(C)40
(D)76
Question(2) A performs 1/5 of the given work in a week. B does the work there in a fortnight. B works only for 3 days by starting the work. After that A completes it. So how many days will he complete?
A एक सप्ताह में दिए गए कार्य का 1/5 करता है | B वहीं कार्य एक पखवारे में कर देता है| B कार्य आरंभ करके केवल 3 दिनों तक कार्य करता है | उसके बाद A उसे पूरा करता है | अतः वह कितने दिनों में पूरा कर देगा ?
(A)28
(B)33
(C)36
(D)43
Question(3) A can do a work within 12 days. B is 60% more efficient than A. Accordingly, how many days can B and A work together?
A एक कार्य 12 दिनों में कर सकता है| B, A की तुलना में 60% अधिक सक्षम है| तदनुसार, B तथा A मिलकर उस कार्य को कितने दिनों में कर सकते है?
(A) 13/22
(B) 60/13
(C) 50/33
(D) 54/23
Question(4) A, B and C can perform one work in 30, 20, 10 days respectively. A gets the support of B in one day work. And the next day, C is supported. This sequence goes ahead. How much time will it take to complete the work accordingly?
A, B तथा C एक कार्य कार्य क्रमशः 30, 20, 10 दिनों में कर सकते है | A को एक दिन के काम में B का सहयोग मिलता है | और अगले दिन C का सहयोग मिलता है | यही क्रम आगे चलता है | तदनुसार काम पूरा होने में कितना समय लगेगा ?
(A) 47/3
(B) 35/7
(C) 65/6
(D) 75/8
Question(5) A and B take the time to work together, A will take more than 4 days to complete that task alone, and B will take 16 days more to complete that task alone. If they work together, will it take days to complete the work?
A और B को मिलकर काम करने में जितना समय लगता है, A को अकेले वह काम पूरा करने में 4 दिन अधिक लगेंगे और B को अकेले वह काम पूरा करने में 16 दिन अधिक लगेंगे | यदि वे दोनों मिलकर काम करें तो काम को पूरा करने दिन लगेंगे ?
(A)8
(B)11
(C)16
(D)13
All Solutions (1-5):
Que(1).Ans-(C)
Que(2).Ans-(A)
Que(3).Ans-(B)
Que(4).Ans-(D)
Que(5).Ans-(A)
Buy online Rajasthan gk book Railway JE CBT REET PAtwari Book SSC CGL Clerk GD Book Buy online Rajasthan gk book Railway JE CBT REET PAtwari Book SSC CGL Clerk GD Book