Mathematics Question For RRB, Railway Group D, Rajasthan SI 19-05-2018

Daily quiz, Math Short Tricks , , , 0 Comments
math important quiz

Railway Group D Recruitment 2018 will be held to recruit candidates to the post in Level 1 of 7 CPC Pay Matrix. … According to Railway Group D Recruitment Notification 2018 and Latest Updates: SBI Clerk (Junior Associates)  Recruitment 2018 And RRB, Railway Group D Railway Loco Pilot Railway Technician DMRC Rajasthan PTET Punjab PTET CTET PSTET BSTC HTET,Bank GK, Latest GK, Reet Exam GK, Rajasthan police Exam Gk, And  Date Wise 19-05-2018 GK Notes Delhi Police Exam GK, SSC CGL Clerk GD Exam GK, HTET Exam GK, CTET Exam GK, PTET Exam GK Questions

mathematics Related Most Question With Answer Set 120 Current Affairs, Aptitude And Join the best Online Test Series & get all India Rank, Logical Match. Logical Problems · Number Series · mathematics and important Question & Answer with solution & Formulas in Hindi & English And Important Questions with Answers to Numerical Ability asked in Gramin Bank Office Assistant Exam And These all questions will very helpful to you for the forthcoming Bank exams, SSC CPO SI Delhi Police and Rajasthan Police and All Competitive Examination.

 

Daily Visit GK on myshort.in

Click: mathematics -Most Question & Answer with Solution

Question.(1) Yogesh and Akshay complete one task in 8 days. The same work can be done in the Akshay and Yuvraj in 24 days, while Yuvraj and Yogesh do the same work in 60/7 days. How many days / time will the Prince do?

 योगेशऔर अक्षय एक कार्य 8 दिनों में पूरा कर लेते हैं | वही कार्य अक्षय तथा युवराज 24 दिनों में कर सकते हैं, जबकि युवराज तथा योगेश वही काम 60/7 दिनों में करते हैं | केवल युवराज उसे कितने दिनों/समय में करेगा ?

(A) 60

(B)65

(C)45

(D)70

Question.(2) The efficiency of A in doing some work is half of B and the efficiency of C is half of the total work capacity of A and B. If C alone completes this task in 40 days, then how many days will the three people work together?

किसी कार्य को करने में A की दक्षता B से आधी है तथा C की दक्षता A तथा B की कुल कार्य क्षमता से आधी है | यदि C अकेले इस कार्य को 40 दिनों में पूर्ण करते हैं तो तीनों व्यक्ति मिलकर काम को कितने दिनों में सम्पन करेगे ?

(A)37 दिन

(B)39 दिन

(C) 40/3 दिनों

(D)36 दिन

Question.(3) Ram and Narendra can work together in 12 days. Ram alone can complete it in 20 days. If Narendra works only every half (1/2) days every day, how many days will Ram and Narendra meet together in the same work?

राम तथा नरेन्द्र मिलकर एक काम को 12 दिन में पूरा कर सकते हैं | राम अकेला उसे 20 दिन में पूरा कर सकता है | यदि नरेन्द्र हर रोज सिर्फ आधा (1/2) दिन काम करे, तो राम और नरेन्द्र मिलकर उसी कार्य को कितने दिन में संपन करेंगे ?

(A)17 दिन

(B)15 दिन

(C)12 दिन

(D)11 दिन

Question.(4) A is three times capable artisan compared to B. Therefore, she completes her work in less than 60 days as compared to her work. According to how many days can those days work together?

A , B की तुलना में तीन गुना सक्षम कारीगर हैं| इसलिए वह एक कार्य B की तुलना में उससे 60 दिन कम में पूरा कर लेता हैं | तदनुसार वे दिनों मिलकर वह कार्य कितने दिनों में कर सकते हैं ?

(A)36 दिन

(B)33 दिन

(C)32 दिन

(D)45/2 दिन

Question.(5) A work done by P and Q is completed in 12 days and in 15 days by Q and R and in R by 20, P alone according to P in how many days can he complete?

 P तथा Q द्वारा एक कार्य 12 दिनों में पूरा कर लिया जाता हैं और Q तथा R द्वारा 15 दिनों में एवं R तथा P द्वारा 20 दिनों में तदनुसार अकेला P उसे कितने दिनों में पूरा कर सकता है ?

(A)30 दिन

(B)45 दिन

(C)34 दिन

(D)39 दिन

All Solutions (1-5)

Que(1).Ans-(A)

Que(2).Ans-(C)

Que(3).Ans-(B)

Que(4).Ans-(D)

Que(5).Ans-(A)