Mathematics Question For Railway Group D,RPF, Rajasthan SI 01-10-2018
Daily quiz, Math Short Tricks 0 CommentsRailway Group D, RPF, Recruitment 2018 will be held to recruit candidates to the post in Level 1 of 7 CPC Pay Matrix.
mathematics Related Most Question With Answer Set 231Current Affairs, Aptitude And Join the best Online Test Series & get all India Rank, Logical Match. Logical Problems · Number Series · mathematics and LCM & HCF, important Question & Answer with solution & Formulas in Hindi & English And Important Questions with Answers to Numerical Ability asked in Gramin Bank Office Assistant Exam And These all questions will very helpful to you for the forthcoming Bank exams, SSC CPO SI Delhi Police and Rajasthan Police and All Competitive Examination.
Click: mathematics -Most Question & Answer with
Question(1) 250 men can complete one work within 20 days by working 5 hours a day. The minimum number of people required to complete the same work within 10 days of working 8 hours per day?
250 आदमी प्रतिदिन 5 घंटे काम करके एक काम को 20 दिन में पूरा कर सकते है | उसी काम को प्रतिदिन 8 घंटे काम करके 10 दिन के भीतर पूरा करने के लिए अपेक्षित आदमियों की न्यूतम संख्या है?
(A) 464
(B) 245
(C) 642
(D) 313
Question(2) A and B can divide 11/19 of a task together. At the same time, B and C can divide 14/19 of the same work. Accordingly, what will be the ratio of the working of A, B, C?
A और B मिलकर एक कार्य का 11/19 भाग कर सकते है | उतने ही समय में Bतथा C मिलकर उसी कार्य का 14/19 भाग कर सकते है | तदनुसार A,B,C के कार्य करने का अनुपात क्या होगा ?
(A) 5:6:8
(B) 3:5:4
(C) 2:7:8
(D) 1:7:5
Question(3) A and B can complete any work in 12 days and 15 days respectively. They started working together, but after 4 days A left the job. How many days have the remaining B alone completed?
A तथा B किसी कार्य को क्रमशः 12 दिन तथा 15 दिन में पूरा कर सकते है | उन्होंने मिलकर कार्य करना शुरू किया, लेकिन 4 दिन बाद A काम छोड़्कर चला गया | शेष कार्य को अकेले B ने आगे कितने दिनों में पूरा किया होगा ?
(A)12
(B)16
(C)6
(D)22
Question(4) A and B can complete any work in 9 and 12 days respectively. If they work alternately every day by starting A, how many days will it take to complete the work?
A तथा B किसी कार्य को क्रमशः 9 तथा 12 दिन में पूरा कर सकते हैं | A के आरंभ करके यदि वे बारी -बारी से एक -एक दिन काम करते हों तो कार्य को पूरा होने में कितने दिन लगेंगे ?
(A) 22/6
(B) 34/3
(C) 24/4
(D) 41/4
Question(5) A and B meet any work in 15 days. 50% more work than a B – a skilled craftsman. How long will A alone take to accomplish that task?
A तथा B मिलकर किसी कार्य को 15 दिन में पूरा करते है| B की तुलना में 50% अधिक कार्य – कुशल कारीगर है | अकेले A को उस कार्य को पूरा करने में कितना समय लगेगा ?
(A)25
(B)37
(C)33
(D)29
All Solutions (1-5):
Que(1).Ans-(D)
Que(2).Ans-(A)
Que(3).Ans-(C)
Que(4).Ans-(D)
Que(5).Ans-(A)