Mathematics Question For RRB, Railway Group D, Rajasthan SI 26-05-2018
Daily quiz, Math Short Tricks 0 CommentsRailway Group D Recruitment 2018 will be held to recruit candidates to the post in Level 1 of 7 CPC Pay Matrix.
mathematics Related Most Question With Answer Set 127 Current Affairs, Aptitude And Join the best Online Test Series & get all India Rank, Logical Match. Logical Problems · Number Series · mathematics and iLCM & HCF, important Question & Answer with solution & Formulas in Hindi & English And Important Questions with Answers to Numerical Ability asked in Gramin Bank Office Assistant Exam And These all questions will very helpful to you for the forthcoming Bank exams, SSC CPO SI Delhi Police and Rajasthan Police and All Competitive Examination.
Click: mathematics -Most Question & Answer with Solution
Question (1) 3 men and 2 women can do one job in 15 days. 2 men and 3 women can do the same work in 18 days. How many days will it take for a man and a woman to do that work?
3 पुरूष और 2 महिलाएऐं एक काम को 15 दिन मे कर सकते है | 2 पुरूष और 3 महिलाऐं उसी काम को 18 दिन में कर सकते है | एक पुरूष और एक महिला को उस काम को करने में कितने दिन लगेगें ?
(A) 410/11 days
(B) 450/11 days
(C) 550/11 days
(D) 440/11 days
Question (2) Yogesh and Yuvraj can complete any work in 12 days and 15 days respectively. Yogesh worked 4 days in the beginning After that he leaves the work and then goes, tell how many days of work alone alone is complete?
योगेश और युवराज किसी कार्य को क्रमशः 12 दिन व 15 दिन में पूरा कर सकते हैं | प्रारम्भ में योगेश ने 4 दिन कार्य किया | इसके बाद वह कार्य छोड़कर चला जाता है तो बताओ शेष कार्य को अकेला युवराज कितने दिनों में पूरा करेगा ?
(A)11 days
(B)15 days
(C)17 days
(D)10 days
Question (3) Raju and Vicky can complete any work in 12 and 18 days respectively. Raju starts the work and after that, he works in one day or so, in how much time will the work be completed?
राजू और विकी किसी कार्य को क्रमशः 12 तथा 18 दिन में पूरा कर सकते हैं | राजू कार्य को आरम्भ करता है तथा उसके बाद वे बारी – बारी से एक -एक दिन कार्य करते हैं तो कार्य कितने समय में पूरा होगा ?
(A) 43/1 days
(B) 43/6 days
(C) 43/3 days
(D) 53/3 days
Question (4) In fulfilling any task, Raju takes 50% more time than Yogesh. If both of them meet together in 18 days, how long will Yogesh alone complete it?
किसी कार्य को पूरा करने में राजू , योगेश से 50 % अधिक समय लेता है | यदि दोनों मिलकर वे इस कार्य को 18 दिन में पूरा करें तो योगेश अकेले उसे कितने समय में पूरा करेगें ?
(A) 15 days (B) 35 days (C) 45 days (D)65 days
Question (5) 50,75,125 और 140 का लघुत्तम समापवर्त्य क्या होगा ?
(A)10023
(B)110022
(C)121233
(D)10500
All Answer
(1) 450/11
(2) 10
(3) 43/3
(4) 45
(5) 10500